EK Oil #1 Welsh

•

MonthProduction – Barrels of Oil EquivalentNotes and Happenings
Jul-260This well has been plugged and abandoned. This will be the final update for this well.
Jun-260Well is being plugged and abandoned.
May-260Well is being plugged and abandoned.
Apr-260Awaiting rig for final recompletion.
Mar-260Awaiting rig for final recompletion.
Feb-260Awaiting rig for final recompletion.
Jan-260Waiting on rig to recomplete EK well.
Dec-250Waiting on rig to recomplete EK well.
Nov-250We have made a successful completion into a sand where hydrocarbons are present. There is also water associated with this sand, and as such, additional work needs to be done on the Salt Water Disposal well associated with the EK #1. This work is still covered by the “turnkey” nature of the project and will be paid for by Cruciform. Once the work is done on the SWD, the well will be turned on and tested for two to four weeks to confirm the commerciality of the zone.
Oct-250The operator was recompleting into current pay sand.
Sep-250The well is being prepared for re-completion, which should be done within the next 30 days.
Aug-2542
Jul-250The well is being prepared for re-completion, which should be done within the next 30 days.
Jun-250The well is being prepared for re-completion, which should be done within the next 30 days.
May-250
Apr-250The well is being prepared for re-completion, which should be done within the next 30 days.
Mar-250The well is being prepared for re-completion, which should be done within the next 30 days.

•